100kW Wind Turbine, Easton Pond Business Center

NE&C installed a Northwind 100 kW wind turbine at our headquarters. The project was unprecedented as it was the first wind turbine in Middletown and the only commercially owned turbine in Rhode Island. NE&C brought the project from conception to completion from the initial meteorological study through design, permitting, and construction management.

Click here for installation and construction pictures and updates

Click here to see the wind turbine simulation videos

Services Provided 

  • Feasibility study
  • Energy assessment study
  • Financial modeling
  • Permitting
  • Foundation design
  • Geotechnical investigations
  • Site design 
  • Procurement
  • Installation
  • Construction
  • Testing
  • Commissioning
  • Power connection